江西煤炭科技2023年第1期摘要:针对龙顶山煤业9103工作面回采至630m处时,回风顺槽距工作面40m范围内出现严重底鼓,导致顺槽设备安装难度大、顺槽成型效果差以及回采难度大的问题,通过分析巷道底鼓机理,拟定采用“深孔卸压+注浆锚索+起底浇筑”联合控制技术解决巷道底鼓问题。经实际应用表明,采取联合控制技术后,9103工作面回风顺槽底鼓量由原来的0.52m控制在0.22m以下,取得了显著应用成效。关键词:回采巷道;底鼓机理;注浆锚索;深孔卸压中图分类号:TD322+.1;TD353+.5文献标识码:A文章编号:1006-2572(2023)01-0037-03PracticeofFloorHeaveControlinEntryofAdvanceStressAreainStopeFaceZhangMin(ShanxiGaopingKexingLongdingshanCoalIndustryCo.,Ltd.,Gaoping,Shanxi048400)Abstract:Inviewofproblemssuchastheseriousfloorheave,thedifficultyinstallmentoftheentryequipment,thepoorshapingeffectoftheentryandthedifficultyofminingwithintherangeof40mfromthereturnairentrytotheworkingface,whileminingat630min9103workingfaceofLongdingshanCoalIndustry,byanalyzingthemechanismofroadwayfloorheave,thecombinedcontroltechnologyof"deepholepressurerelief,groutinganchorcableandbottomingpouring"isproposedtosolvetheproblemofroadwayfloorheave,whosepracticalapplicationshowsthatthefloorheaveofthereturnairgatewayat9103workingfaceiscontrolledbelow0.22mwiththeoriginal0.52m.Keywords:gateway;mechanismoffloorheave;groutinganchorcable;deepholepressurerelief回采面超前应力区顺槽底鼓治理技术实践张敏(山西高平科兴龙顶山煤业有限公司,山西高平048400)综采工作面在回采过程中在工作面前方30~50m范围内产生应力影响区,当工作面过断层、采空区、老空区时出现应力集中现象,从而导致应力影响区巷道围岩出现应力显现现象,主要表现在两帮收拢、顶板下沉、底板鼓起等[1-4]。一旦出现底板鼓起现象时,不仅影响巷道成型率,无法保证巷道断面规格,而且底板鼓起降低了两帮支撑强度,很容易造成两帮煤体垮落,不利于工作面后期安全回采。本文以龙顶山9103工作面为工程实例,对工作面回采过程中运输顺槽底鼓原因进行分析探讨后,再采取有效应对措施解决巷道严重底鼓的问题。1工程概况山西高平科兴龙顶山煤业有限公司9103工作面布置在9101采区以北,工作面以北为实煤区,以南为9101工作面采空区,以东依次布置采...